FY 2024 Major Projects

The new Leinweber Computer Science and Information Building
Projects in Planning

Horace H. Rackham Educational Memorial

University of Michigan Health

  • Michigan Medicine Childcare Facility
  • C.S. Mott Children’s and Von Voigtlander Women’s Hospitals New Children’s Emergency Services Fast Track Clinic
  • Oakland County Ambulatory Care Expansion
  • A. Alfred Taubman Health Care Center Fire Alarm Replacement
  • University Hospital South Renovation
Projects in Progress

William Davidson Player Development Center Renovate and Expand Team Areas | Work started January 2024 with an estimated completion date of December 2024. Financing is from Athletic department gifts.

Dearborn Renick University Center First Floor Renovations | Work started March 2024 with an estimated completion date of December 2024. Financing is from UM-Dearborn.

Electric Vehicle Center Battery Laboratory Expansion Leasehold Improvements | Work started February 2024 with an estimated completion date of December 2024. Financing is from the College of Engineering.

Flint College Of Innovation and Technology Building | Work started March 2024 with an estimated completion date of March 2026. Financing is from a United States Department of Commerce Economic Development Administration grant, a Mott Foundation grant, gifts and UM-Flint.

Edward and Rosalie Ginsberg Building | Work started May 2023 with an estimated completion date of June 2025. Financing is from a gift.

Hadley Family Recreation and Well-Being Center (Central Campus Recreation Building Replacement) | Work started December 2022 with an estimated completion date of June 2025. Financing is from reserves and Student Life.

Hayward Street Geothermal Facility | Work started January 2023 with an estimated completion date of March 2025. Financing is from reserves.

Leinweber Computer Science and Information Building | Work started May 2022 with an estimated completion date of September 2025. Financing is from state capital appropriation, the Office of the Provost, the College of Engineering and the School of Information.

Marsal Family School of Education at Marygrove Leasehold Improvements | Work started December 2023 with an estimated completion date of December 2024. Financing is from tenant improvement allowance and the Marsal Family School of Education.

Medical Science Unit I B and D Wings Renovation | Work started March 2023 with an estimated completion date of December 2025. Financing is from the Medical School.

New Building for the College of Pharmacy | Work started February 2023 with an estimated completion date of December 2025. Financing is from reserves and gifts.

New Central Campus Residential Development | Work started September 2023 with an estimated completion date of September 2026. Financing is from reserves.

New Michigan Marching Band Practice Field | Work started February 2023 with an estimated completion date of August 2024. Financing is from reserves.

Observatory Hall Reserve Officers Training Corps Space Renovation | Work started March 2024 with an estimated completion date of September 2025. Financing is from reserves and the Office of the Provost.

Glenn E. Schembechler Hall Renovate Team Locker Room | Work started January 2024 with an estimated completion date of September 2024. Financing is from Athletic department gifts.

School of Nursing Building 1 Classroom and Interior Renovation | Work started March 2024 with an estimated completion date of December 2024. Financing is from the School of Nursing.

U-M Center for Innovation | Work started December 2023 with an estimated completion date of June 2027. Financing is from a gift, a state grant and development activities.

University of Michigan Health | Financing is from University of Michigan Health.

  • D. Dan and Betty Kahn Health Care Pavilion | Work restarted May 2021 with an estimated completion date of June 2025.

  • Rogel Cancer Center Infrastructure Upgrades | Work started June 2024 with an estimated completion date of March 2026.

  • A. Alfred Taubman Health Care Center Air Handling Unit Replacement | Work started May 2024 with an estimated completion date of March 2026.

  • U-M Health Clinical Expansion Project | Work started January 2023 with an estimated completion date of September 2024. Financing is from tenant improvement allowance and University of Michigan Health.

  • University Hospital Electrical Substation Replacement | Work started July 2022 with an estimated completion date of September 2024.

Projects Completed

Bonisteel Boulevard Water Main and Road Reconstruction | Completed August 2023. Financed by reserves and utility reserves.

Center for Academic Innovation Leasehold Improvements | Completed July 2023. Financed by tenant improvement allowance and reserves.

Climate and Space Research Building Leinweber Space Innovation Laboratory Renovation | Completed April 2024. Financed by the College of Engineering.

East University Chiller Plant Chiller Replacement | Completed August 2023. Financed by utility reserves.

Environmental and Water Resources Engineering Building and George Granger Brown Memorial Laboratories Civil and Environmental Engineering Project | Completed October 2023. Financed by the College of Engineering.

Michigan Stadium Scoreboard Replacement | Completed November 2023. Financed by the Athletic department.

President’s Residence Infrastructure Renovation | Completed September 2023. Financed by reserves.

Recreational Sports Fields Hubbard Road, North Campus | Completed November 2023. Financed by Student Life.

School of Social Work Chiller Replacement | Completed May 2024. Financed by reserves and utility reserves.

University of Michigan Health | Financed by University of Michigan Health.

Specialty Pharmacy Expansion | Completed October 2023.

Brighton Center for Specialty Care Linear Accelerator Expansion | Completed July 2023.

Brighton Center for Specialty Care Shell Space Utilization For New Operating Rooms | Completed August 2023.

Courtyard Infrastructure Improvements and Restoration | Completed April 2024. Financed by reserves and utility reserves.

Mott Children’s and Von Voigtlander Women’s Hospitals New Birth Center Patient Rooms | Completed May 2024.

University Hospital and University Hospital South Clinical Pathology Laboratories | Completed January 2024.

University Hospital Pneumatic Tube Expansion | Completed January 2024.